GSK - ViiV - Attachment Inhibitor Project
(2017-2018)

Novartis Vaccines - Summer and Winter Shutdown
(2014)

GSK Vaccines - Site Shutdown
(2015-2018)

GSK Vaccines - New QC Labs Project
(2015-2017)
-
GSK - ViiV - Attachment Inhibitor Project
(2017-2018)- Attachment Inhibitor Project - Parma
- Scopo dei servizi: Project Management, Project Control, Process Equipment expediting
- Anno: 2017-2018
- Luogo :
- Stima Investimento: 30 Mil.€
- Durata: 12 Mesi
-
Novartis Vaccines - Summer and Winter Shutdown
(2014)- Summer and Winter Shutdown Vaccines Primary - Rosia
- Scopo dei servizi: Project Management and Project Control
- Anno: 2014
- Luogo : Rosia - Siena
- Stima Investimento:NA
- Durata: 24 Giorni, 20.000 Working Hours, 7/7 Working days, night shift at peak
-
GSK Vaccines - Site Shutdown
(2015-2018)- Primary, Secondary, Packaging, UtilitiesSite Shutdown October 2016- Rosia
- Scopo dei servizi: Project Management and Project Control for all Site
- Anno: 2016-18
- Luogo : Rosia - Siena
- Stima Investimento:NA
- Durata: 24 Giorni, 100.000 Working Hours, 7/7 Working days, night shift at peak
-
GSK Vaccines - New QC Labs Project
(2015-2017)- New Quality Control Labs - Rosia
- Scopo dei servizi: Project Management and Project Control
- Anno: 2015-2017
- Luogo : Rosia - Siena
- Stima Investimento: 50 Mil.€
- Durata: 24 Mesi